Mill Conversion - Residential Apartments, Hackney

 

Mill Conversion - Residential Apartments, Hackney

Conversion of an existing mill into 50 apartments over 10 floors complete with new basement and retail units to ground floor for Collent Street Property.

Initial works involved the demolition of existing industrial building with the retention of two elevations, followed by the excavation of a basement area over the whole site. The main structural element of the building was insitu concrete installed with the use of a tower crane. The external envelope was generally sip panels and rainscreen cladding punctuated with upvc windows and doors. Internally partitions were constructed using metal stud partition and plasterboard.

The project was completed to a full turnkey situation allowing the new owner to move directly in.